EdgeConneX Appeals Rejection of Data Center Proposal, Asserting Grid Capacity and Fuel Source Capabilities

EdgeConneX Ireland has recently lodged an appeal with An Bord Pleanála against the rejection of its data center proposal by the South Dublin County Council. The company sought to develop two adjoining data centers on its Dublin Campus located in the town of Ballmakaily in Lucan, Dublin. Despite facing opposition from the council, EdgeConneX maintains that its proposal is viable and aligns with their development plan.

Basis for Rejection by South Dublin County Council

The rejection by South Dublin County Council stemmed predominantly from two reasons. Firstly, the council highlighted concerns regarding insufficient capacity in the grid, which could potentially hinder the operation of the proposed data centers. Additionally, it was pointed out that EdgeConneX did not have a fixed connection agreement in place, further raising doubts about the feasibility of the project.

EdgeConneX’s Argument in the Appeal

In its appeal, EdgeConneX contends that the council has adopted an “unduly rigid approach” to their development plan and that their proposal has been misinterpreted. The company emphasizes that it already has an existing connection agreement with EirGrid, thereby contradicting the council’s claim of a lack of a fixed connection agreement. Furthermore, EdgeConneX firmly denies the existence of any capacity issues, asserting that it has taken appropriate measures to ensure the project’s smooth operation.

Power Source for the Data Center

One crucial aspect that EdgeConneX has outlined in its appeal is its plan to power the data center through a gas-powered generation plant in the short to medium term. While acknowledging the concerns around the grid’s capacity, the company aims to mitigate such issues by relying on an alternative energy source. Additionally, EdgeConneX emphasizes its commitment to transitioning to renewable energy when it becomes readily available, highlighting the data center’s flexibility and potential to benefit the stability of the grid.

Previous Approval for Building Expansion and Power Generation

It is worth noting that EdgeConneX had secured approval for two new buildings at the same Dublin Campus in the previous year. The company’s plans also included the installation of three gas-powered generation plants and 32 standby generators. This prior approval indicates that EdgeConneX’s proposed data center development aligns with the local planning regulations, making their current appeal all the more significant.

EirGrid’s Moratorium on New Data Centers

The challenges faced by EdgeConneX are not unique, as Ireland’s state-owned electric power transmission operator, EirGrid, imposed a de facto moratorium on new data centers in Dublin until 2028. This decision, implemented in January 2022, has adversely impacted the development of data centers in the region, making EdgeConneX’s appeal even more critical in light of the broader industry context.

Appeal by Vantage Data Centers

Adding to the ongoing debate surrounding data center development in Dublin, Vantage Data Centers has also filed an appeal against a rejected data center proposal. Their appeal was lodged in July, and a decision is expected in October 2023. The outcome of Vantage Data Centers’ appeal could potentially have significant implications for the future of data center development in the region.

EdgeConneX’s appeal against the rejection of its data center proposal demonstrates the company’s determination to proceed with its plans on the Dublin Campus. Challenging the council’s concerns over grid capacity and the lack of a fixed connection agreement, EdgeConneX seeks to prove the viability of the project. Moreover, the company’s commitment to employing a gas-powered generation plant and transitioning to renewable energy showcases their dedication to sustainable practices. As the outcome of EdgeConneX’s appeal and Vantage Data Centers’ appeal approaches, the decisions made will undoubtedly impact the future landscape of data center development in Dublin.

Explore more

Resilience Becomes the New Velocity for DevOps in 2026

With extensive expertise in artificial intelligence, machine learning, and blockchain, Dominic Jainy has a unique perspective on the forces reshaping modern software delivery. As AI-driven development accelerates release cycles to unprecedented speeds, he argues that the industry is at a critical inflection point. The conversation has shifted from a singular focus on velocity to a more nuanced understanding of system

Can a Failed ERP Implementation Be Saved?

The ripple effect of a malfunctioning Enterprise Resource Planning system can bring a thriving organization to its knees, silently eroding operational efficiency, financial integrity, and employee morale. An ERP platform is meant to be the central nervous system of a business, unifying data and processes from finance to the supply chain. When it fails, the consequences are immediate and severe.

When Should You Upgrade to Business Central?

Introduction The operational rhythm of a growing business is often dictated by the efficiency of its core systems, yet many organizations find themselves tethered to outdated enterprise resource planning platforms that silently erode productivity and obscure critical insights. These legacy systems, once the backbone of operations, can become significant barriers to scalability, forcing teams into cycles of manual data entry,

Is Your ERP Ready for Secure, Actionable AI?

Today, we’re speaking with Dominic Jainy, an IT professional whose expertise lies at the intersection of artificial intelligence, machine learning, and enterprise systems. We’ll be exploring one of the most critical challenges facing modern businesses: securely and effectively connecting AI to the core of their operations, the ERP. Our conversation will focus on three key pillars for a successful integration:

Trend Analysis: Next-Generation ERP Automation

The long-standing relationship between users and their enterprise resource planning systems is being fundamentally rewritten, moving beyond passive data entry toward an active partnership with intelligent, autonomous agents. From digital assistants to these new autonomous entities, the nature of enterprise automation is undergoing a radical transformation. This analysis explores the leap from AI-powered suggestions to true, autonomous execution within ERP